Oklahoma

PRELIMINARY NOTICE

Lienor must sent pre-lien notice within (75) days after the last date of supply of material, services, or labor. Okla. Stat. Ann. tit. 42, § 142.6 (West).

CONTENTS OF PRELIMINARY NOTICE

The date of filing; name and address of the lienor and subject of the lien and the owner of the property; a legal description of the property; and the amount claimed. Okla. Stat. Ann. tit. 42, § 143.1 (West).

WHEN COMPLETION OCCURS

Original contractor claiming a lien must file with county clerk where property located, within four months after last date labor and materials were furnished. Okla. Stat. 42, § 142 (West).

TIME LIMIT FOR RECORDING MECHANICS LIEN

Statement shall be filed with court clerk within four (4) months after the date upon which last material, services, or labor was furnished upon the subject property. Okla. Stat. Ann. tit. 42, § 142 (West).

TIME LIMIT FOR ENFORCING MECHANICS LIEN

The lien provided for in the preceding section1 shall not be effective unless suit shall be brought within one year after it accrued. Okla. Stat. Ann. tit. 42, § 149 (West).

FORECLOSURE OR DISMISSAL BY COURT

Upon full payment of lien plus court costs. Okla. Stat. Ann. tit. 42, § 147.1 (West).

https://oksenate.gov/sites/default/files/2019-12/os42.pdf