Delaware

PRELIMINARY NOTICE

Within 10 days of request (owner not required to pay until received) § 270.

CONTENTS OF PRELIMINARY NOTICE

Written list of all persons who have provided labor, materials, or both. § 2705.

WHEN COMPLETION OCCURS

Upon purported completion; duration of statute of limitations; 90% of owing received; certificate of occupancy issued; owner issues certificate of completion; or when final payment is due.

TIME LIMIT FOR RECORDING MECHANICS LIEN

Direct contractors must file statement of lien within 180 days after date of completion. § 2711(a). All others must file statement of claim within 120 days of the last delivery or completion of work. § 2711(b).

TIME LIMIT FOR ENFORCING MECHANICS LIEN

The proceedings to recover the amount of any claim shall be by writ of scire facias. Foreclosure (via writ) and the filing of the statement of claim are concurrent. §§ 2714, 2715, 2727.

FORECLOSURE OR DISMISSAL BY COURT

Not applicable.