Florida

PRELIMINARY NOTICE

Lienors other than direct contractors must serve Notice to Owner within 45 days of supplying labor, services, or materials and before final payment.

CONTENTS OF PRELIMINARY NOTICE

Amount due claimant; amount of demand; and must fairly apprise owner and public of the nature and amount of the demand.

WHEN COMPLETION OCCURS

Upon the last date that the lienor furnishes labor, services, or materials required under the contract, and not by other standards such as occupancy or final inspection.

TIME LIMIT FOR RECORDING MECHANICS LIEN

Within 90 days after final furnishing of labor, services, or materials by lienor. TIME LIMIT FOR ENFORCING MECHANICS LIEN No lien is valid for more than one year from the date of recording the Claim of Lien.

FORECLOSURE OR DISMISSAL BY COURT

A lien foreclosure  action must be filed within one year of the date of recording

https://flsenate.gov/Laws/Statutes/2022/Chapter713