Nevada
PRELIMINARY NOTICE
Notice of Right to Lien may be served at any time, but gives a right to lien for work performed up to 31 days before service and after until completion. NRS § 108.245(6).
CONTENTS OF PRELIMINARY NOTICE
General description of the work/services performed; identification of the property; and identification of the general contractor or subcontractor with whom contracted. NRS § 108.245.
WHEN COMPLETION OCCURS
Actual completion; occupation by owner and cessation of work; acceptance of the work by owner and cessation of work; or cessation of work for 30 consecutive days if notice of completion is timely recorded. NRS § 108.22116.
TIME LIMIT FOR RECORDING MECHANICS LIEN
Within 90 days after completion or latest delivery of material/ equipment/labor, whichever is latest, or within 40 days after recording a valid notice of completion. NRS § 108.226(1).
TIME LIMIT FOR ENFORCING MECHANICS LIEN
Within 6 months of the recording of the notice of lien; or the time may be extended for up to 1 year in writing and signed by the claimant and a person with an interest in the property. NRS § 108.233.
FORECLOSURE OR DISMISSAL BY COURT
If an action to enforce a claim of lien isn’t brought to trial within 2 years of commencement of the action to enforce the lien, the court may dismiss; if action is not brought to trial within 5, court shall dismiss. NRCP § 41(e).